Rockdale Technology Part 1
SDP Acquisitions. Filed.
SDP Acquisitions, an affiliate of Atlanta based Strategic Real Estate Partners, filed a state Development of Regional Impact application for a 53 acre, three warehouse data center campus totaling about 837,500 square feet at 1975 Sigman Road NW in Conyers, Rockdale County. The developer is seeking rezoning, with a target completion year of about 2028.
Follow this project
One free email when Rockdale Technology Part 1 changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Filed
- Operator
- Not disclosed
- Applicant on record
- SDP Acquisitions
- Location
- 1975 Sigman Road NW, Conyers, Rockdale County, GA
- Size
- MW not reported, 53 acres, 837,500 sq ft
- Cooling
- Not reported
- Utility
- Not reported
- First reported
- 2026
- Last updated
- January 1, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Large data center campus proposed for 53-acre site east of Atlanta, Atlanta Journal-Constitution
- Data center campus proposed by Strategic Real Estate Partners outside Atlanta, Georgia, Data Center Dynamics
What it would mean nearby
Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. Real-time pricing revenue credit and cost allocation review (docket 57171) is pending before the commission without a published residential figure yet. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Rockdale Technology Part 1 data center?
It is in Conyers, Rockdale County, GA.
Has the Rockdale Technology Part 1 data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the Rockdale Technology Part 1 data center?
Reported size: 53 acres, 837,500 square feet.
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.