Is a Data Center Coming

Georgia

Data centers in Rockdale County

We track 3 projects inside Rockdale County and 19 more within 25 miles of it. For a distance-specific answer, check your own address.

In Rockdale County

Under construction 154 MW Conyers

DC BLOX broke ground in September 2024 on a hyperscale data center campus off Farmer Road and Lester Road in Conyers, Rockdale County, on about 72 acres. The plan calls for a 10 megawatt building plus three 48 megawatt buildings (about 154 critical megawatts committed and planned) totaling roughly 748,000 square feet, using air cooled chillers with thermal storage, plus a large electrical substation. A hyperscale tenant anchors the first phase, which was targeted for delivery in late 2025.

Filed MW not reported Conyers

SDP Acquisitions, an affiliate of Atlanta based Strategic Real Estate Partners, filed a state Development of Regional Impact application for a 53 acre, three warehouse data center campus totaling about 837,500 square feet at 1975 Sigman Road NW in Conyers, Rockdale County. The developer is seeking rezoning, with a target completion year of about 2028.

On hold MW not reported Conyers

Atlanta based Grind Capital Group proposed a data center on Irwin Bridge Road in Conyers, Rockdale County, about half a mile from the DC BLOX site, describing it as a multi billion dollar investment. As of an April 2026 report, the application had been voluntarily deferred and was awaiting review under the county's new unified development ordinance amid a data center moratorium, with mixed community reaction at a scheduled May 12 meeting.

Within 25 miles of Rockdale County

CenturyLink Operator not disclosed
21 mi WOperatingFulton County, GA
QTS Suwanee Quality Technology Services
24 mi NOperatingGwinnett County, GA

Power bills in Rockdale County

Most of the county is served by Georgia Power, with parts on Snapping Shoals EMC or Walton EMC.

Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026. The December 2025 certification of about 9,885 MW of new generation for data center load came with a promise of at least $8.50 a month of downward pressure on a typical bill in 2029 through 2031, because large customers are meant to carry more of the cost. Consumer groups warned it could instead add around $20 a month if the projected data center demand does not show up.

Georgia Power and the Georgia PSC Public Interest Advocacy Staff reached a stipulated agreement extending the alternate rate plan first approved in the 2022 rate case, keeping Georgia Power base electricity rates flat through at least 2028. The Georgia Public Service Commission approved the stipulation by vote on July 1, 2025, with a formal order issued July 31, 2025. The freeze applies only to base rates and does not limit separate fuel cost recovery or storm cost recovery charges, both of which can still change a residential bill during the freeze period. Georgia Power has said growth in large load customers such as data centers helped make the freeze possible by spreading fixed costs across a larger customer base.

Alerts for Rockdale County

One email when a filing, hearing or status changes within 25 miles of the county seat. For a tighter radius, check your own address and subscribe there.

Unsubscribe with one click. We do not sell the list.