Project STAMP Data Center (Stream Data Centers)
Stream Data Centers. Filed, 500 MW
Dallas based Stream Data Centers, backed by Apollo Global Management, wants to build a roughly 19.5 billion dollar, three building, 2.2 million square foot data center complex on about 90 acres of the STAMP megasite in the town of Alabama, drawing up to 500 megawatts at full buildout. The company is seeking about 1.46 billion dollars in sales tax and mortgage recording tax abatements from the Genesee County Industrial Development Agency, among the largest incentive packages ever proposed in the state. The project has become a flashpoint in New York's broader data center fight, including a July 2026 statewide moratorium on new data center permits and questions about a possible conflict of interest at the IDA.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Project STAMP Data Center (Stream Data Centers) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- Stream Data Centers
- Applicant on record
- Stream Data Centers
- Location
- Alabama, Genesee County, NY (approximate, city center)
- Size
- 500 MW, 90 acres, 2,200,000 sq ft
- Cooling
- Not reported
- Utility
- New York Power Authority
- Last updated
- September 24, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Tax breaks for Genesee County data center among highest ever, Investigative Post, 2026-03-18
- A $19.5B data center and a statewide pause: What's at stake in Genesee County, Rochester Business Journal, 2026-06-15
- Genesee County IDA has 'conflict of interest' in data center project, Investigative Post, 2026-01-30
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 500 MW facility would draw roughly 1.6 million to 5.7 million gallons of water a day, about what 18,200 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the Project STAMP data center?
It is in Alabama, Genesee County, NY.
Has the Project STAMP data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the Project STAMP data center?
Reported size: 500 MW, 90 acres, 2,200,000 square feet.