Vantage Data Centers. Under construction. 160 MW.

Vantage Data Centers is building a three-building campus of roughly 160 megawatts at the southeast corner of Van Buren Street and Bullard Avenue in Goodyear, with the city having approved a second phase of the project. At full build-out the 50-acre campus is expected to total more than one million square feet.

Status
Under construction
Operator
Vantage Data Centers
Applicant on record
Vantage Data Centers
Location
45 S Bullard Ave, Goodyear, AZ 85338, Maricopa County, AZ
Size
160 MW, 50 acres, 1,000,000 sq ft
Cooling
Not reported
Utility
Arizona Public Service
Last updated
August 19, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 160 MW facility would draw roughly 507,000 to 1.8 million gallons of water a day, about what 5,800 households use.

Arizona Public Service is asking the commission for a 16.4% residential increase (2025 general rate case (docket E-01345A-25-0105)). On a $160 monthly bill that is about $22 to $30 a month.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

PHX-10 Microsoft
2.7 mi SOperatingMaricopa County, AZ
Project Baccara Operator not disclosed
10 mi NApproved 700 MW Maricopa County, AZ
Lumen Lumen Technologies
18 mi EOperatingMaricopa County, AZ

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.