Is a Data Center Coming

Maricopa County, AZ

Compass PHX II Campus

Compass Datacenters. Filed. 108 MW.

Compass Datacenters is proposing PHX II, a three-building, 108 megawatt campus at the southwest corner of El Mirage Road and Peoria Avenue after paying 79.3 million dollars for 121 acres. The company submitted a site plan review request to the El Mirage Planning and Zoning Commission in February 2024.

Status
Filed
Operator
Compass Datacenters
Applicant on record
Compass Datacenters
Location
SW corner of El Mirage Road and Peoria Avenue, El Mirage, AZ, Maricopa County, AZ
Size
108 MW, 121 acres, 624,000 sq ft
Cooling
Not reported
Utility
Arizona Public Service
First reported
2024-02
Last updated
August 19, 2026

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 108 MW facility would draw roughly 342,000 to 1.2 million gallons of water a day, about what 3,900 households use.

Arizona Public Service is asking the commission for a 16.4% residential increase (2025 general rate case (docket E-01345A-25-0105)). On a $160 monthly bill that is about $22 to $30 a month.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Project Baccara Operator not disclosed
3.4 mi NWApproved 700 MW Maricopa County, AZ
PHX-10 Microsoft
10 mi SOperatingMaricopa County, AZ

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.