Is a Data Center Coming

Ozaukee County, WI

Vantage Data Centers Lighthouse Campus (Port Washington)

Vantage Data Centers (filed as Cloverleaf Infrastructure). Under construction

Vantage Data Centers, working from land assembled by Cloverleaf Infrastructure, broke ground in December 2025 on a data center campus on the north side of Port Washington that could grow to as much as 1,900 acres and around 3.5 gigawatts of power, potentially the largest single electricity user in Wisconsin. The project is linked to OpenAI and Oracle's Stargate initiative. In August 2026, 66 percent of Port Washington voters approved a ballot measure requiring voter approval before the city can grant future tax incentives over 10 million dollars to developers.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Under construction
Operator
Vantage Data Centers
Applicant on record
Cloverleaf Infrastructure
Location
Dixie Road, Port Washington, WI, Ozaukee County, WI
Size
MW not reported, 1900 acres
Cooling
Not reported
Utility
We Energies
First reported
2025-01
Last updated
August 29, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

We Energies is asking the commission for a 9.3% residential increase (We Energies general electric and gas rate case for 2027 and 2028 (docket 5-UR-112)). On a $160 monthly bill that is about $13 to $17 a month. This tariff does not change home electric rates by itself, but it is meant to make large new data centers pay the full cost of the power plants and lines built to serve them instead of spreading those costs across everyone's bill. Transmission upgrades like this are typically billed to every electric customer in the state through transmission charges, not just to the data center that made the new line necessary, which is why the cost allocation question matters for ordinary bills even outside the four counties involved.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

Common questions

Where is the Vantage Data Centers Lighthouse Campus (Port Washington)?

It is in Port Washington, Ozaukee County, WI.

Has the Vantage Data Centers Lighthouse Campus (Port Washington) been approved?

Yes, it was approved and is now under construction.

How big is the Vantage Data Centers Lighthouse Campus (Port Washington)?

Reported size: 1900 acres.

Corrections and tips: use the address in the footer. We link every claim to its source.