Data centers in Niagara County

We track 3 projects inside Niagara County and 5 more within 25 miles of it. For a distance-specific answer, check your own address.

In Niagara County

Under construction 360 MW Somerset

TeraWulf's Lake Mariner campus, built on the site of the former Somerset coal fired power plant on Lake Ontario, is adding two new AI data center buildings on 61 acres in the parcel's northeastern corner, part of a 3.2 billion dollar expansion that would raise the 410 acre campus to 360 megawatts of capacity. The Niagara County Planning Board and the Somerset Town Board both gave unanimous approval to the required Planned Unit Development amendment, site plan, state environmental review, and special use permit in late 2025, and construction is underway with new operations expected in the second half of 2026, creating about 200 new jobs.

Operating MW not reported

An operating Blockfusion data center site in Niagara County, NY, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 16,000 square feet of building is mapped.

Operating MW not reported

An operating US Bitcoin data center site in Niagara County, NY, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 62,000 square feet of building is mapped.

Within 25 miles of Niagara County

Power bills in Niagara County

Most of the county is served by National Grid.

Every New York rate case in dollars a month, with hearing dates: willmybillgoup.com, our rate case tracker.

Alerts for Niagara County

An email when a filing, hearing, or status changes within 25 miles of the county seat. For a tighter radius, check your own address and subscribe there.

Unsubscribe with one click. We do not sell the list.

Want this worked out for one address? The address report covers noise, water, your power bill, and what is being planned nearby. See the address report.