Is a Data Center Coming

Stark County, OH

DAMAC Digital Canton Data Center

DAMAC Digital Solution Ohio LLC. Filed

DAMAC Digital Solution Ohio LLC, a Dubai based company, purchased eight parcels for 36.5 million dollars in December 2025 and is planning a data center of more than one billion dollars on about 85 acres northeast of Trump Avenue SE and Orchardview Drive SE in Canton, a separate site from Corscale's Millerton Street proposal nearby. The company held a community forum on July 14, 2026 and expects construction to start in 2026 with a first building operational in early 2028, but it remains unresolved whether Canton's new citywide data center zoning ordinance, adopted July 27, 2026 on an 8 to 3 council vote, applies to this already annexed site. No final customer or operator has been publicly identified.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Filed
Operator
DAMAC Digital Solution Ohio LLC
Applicant on record
DAMAC Digital Solution Ohio LLC
Location
Canton, Stark County, OH
Size
MW not reported, 85 acres
Cooling
Not reported
Utility
Not reported
First reported
2026-07
Last updated
October 12, 2026

What happens next

Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.

Sources

History

October 12, 2026

Added as filed

Other tracked projects within 25 miles

Involta-Akron Operator not disclosed
22 mi NWOperatingSummit County, OH

Common questions

Where is the DAMAC Digital Canton data center?

It is in Canton, Stark County, OH.

Has the DAMAC Digital Canton data center been approved?

Not yet. An application has been filed and has not been decided.

How big is the DAMAC Digital Canton data center?

Reported size: 85 acres.

Corrections and tips: use the address in the footer. We link every claim to its source.