Is a Data Center Coming

Wayne County, MI

"Project Cannoli" Google Data Center (Van Buren Township)

Google (filed as Panattoni Development). Approved, 1000 MW

Google and developer Panattoni want to build a 1 gigawatt data center called Project Cannoli on 282 acres (150 developed, 132 left as open space) near I-94 and I-275 in Van Buren Township, expected to start running in December 2027 and reach full load a year later. The township board approved rezoning 5 to 2 in February 2026, the Michigan Public Service Commission approved DTE Electric's power contracts on October 1, 2026, and on October 14, 2026 the township Planning Commission voted 5 to 1 to approve the final site plan and a high voltage switching station, after Wayne County and the township also approved a 125 million dollar tax break. Underground work to run a new electric transmission line to the site is already underway with planned road closures near Haggerty Road into 2027, but Panattoni says it has not yet broken ground on the buildings themselves and still hopes to start construction before the end of 2026, while opponents have more than 1,300 petition signatures and a recall effort against supportive township board members.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Approved
Operator
Google
Applicant on record
Panattoni Development
Location
Van Buren Township, Wayne County, MI (approximate, city center)
Size
1000 MW, 282 acres
Cooling
Not reported
Utility
DTE Electric
First reported
2025-12
Last updated
October 19, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 1000 MW facility would draw roughly 3.2 million to 11.4 million gallons of water a day, about what 36,500 households use.

DTE Electric is asking the commission for a 9.7% residential increase (2027 electric rate case (docket U-22046)). On a $160 monthly bill that is about $13 to $18 a month. 2026 electric distribution rate case (docket U-21860) raised residential rates 4.1% from March 2026: about $6 to $8 a month on a $160 bill. The order is meant to keep this one data center's power costs off the bills of regular DTE residential customers, but critics argue the fast, largely ex parte approval process did not fully test that promise.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

Other tracked projects within 25 miles

Comcast Comcast
15 mi EOperatingWayne County, MI

Common questions

Where is the "Project Cannoli" Google data center?

It is in Van Buren Township, Wayne County, MI.

Has the "Project Cannoli" Google data center been approved?

Yes, it has been approved.

How big is the "Project Cannoli" Google data center?

Reported size: 1000 MW, 282 acres.

Corrections and tips: use the address in the footer. We link every claim to its source.