Google and developer Panattoni want to build a 1 gigawatt data center called Project Cannoli on 282 acres (150 developed, 132 left as open space) near I-94 and I-275 in Van Buren Township, expected to start running in December 2027 and reach full load a year later. The township board approved rezoning 5 to 2 in February 2026, the Michigan Public Service Commission approved DTE Electric's power contracts on October 1, 2026, and on October 14, 2026 the township Planning Commission voted 5 to 1 to approve the final site plan and a high voltage switching station, after Wayne County and the township also approved a 125 million dollar tax break. Underground work to run a new electric transmission line to the site is already underway with planned road closures near Haggerty Road into 2027, but Panattoni says it has not yet broken ground on the buildings themselves and still hopes to start construction before the end of 2026, while opponents have more than 1,300 petition signatures and a recall effort against supportive township board members.
Data centers in Wayne County
We track 8 projects inside Wayne County and 6 more within 25 miles of it. For a distance-specific answer, check your own address.
In Wayne County
Raeden and Cal Realty, a Ferragon Corp company, want to convert an existing building at 27800 West Jefferson Avenue in Gibraltar, on the old McLouth Steel industrial site, into a 100 megawatt AI data center. Gibraltar's City Council passed a one year moratorium on data centers in March 2026 after the company filed its site plan application, and in August 2026 the developers sued the city in federal court, arguing the moratorium unfairly blocks a review they are entitled to under existing rules. The lawsuit is pending.
An operating Comcast data center site in Wayne County, MI, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 1,000 square feet of building is mapped.
An operating Quicken Loans data center site in Wayne County, MI, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 46,000 square feet of building is mapped.
An operating US Signal data center site in Wayne County, MI, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 25,000 square feet of building is mapped.
An operating Verizon Wireless data center site in Wayne County, MI, mapped in OpenStreetMap and the IM3 Open Source Data Center Atlas. About 25,000 square feet of building is mapped.
A company called Solstice Data proposed a 26 megawatt data center near homes and a high school in Allen Park, a Detroit suburb. After the city's planning commission postponed a vote three times over incomplete traffic, sound, and engineering studies, it rejected the site plan 7 to 2 in June 2026. City officials are also weighing their own six month moratorium to write clearer rules before the next proposal arrives.
Developer Robert Kato of Klever Technology Center LLC proposed converting a vacant 40,000 square foot warehouse at 27181 Southern Street in Inkster into a data center, citing about 75 million dollars in facility improvements plus up to 250 million dollars of server equipment and 90 to 100 jobs. The Planning Commission had recommended conditional approval, but after residents packed Inkster City Hall on October 19, 2026 to raise concerns about round the clock noise, generator emissions, and light pollution at a site about 100 feet from homes, no council member made a motion to approve the permit on October 20, 2026, effectively killing it. Kato said he will not appeal and does not plan to pursue a data center at that location, telling reporters the project will instead proceed in a neighboring municipality.
Within 25 miles of Wayne County
Want this worked out for one street address? The address report, $19, covers what is being planned near it, your county's rules, and what each nearby site could mean for noise, water, and your bill. See the address report.
Power bills in Wayne County
Most of the county is served by DTE Electric.
DTE Electric is asking the commission for a 9.7% residential increase (2027 electric rate case (docket U-22046)). On a $160 monthly bill that is about $13 to $18 a month. 2026 electric distribution rate case (docket U-21860) raised residential rates 4.1% from March 2026: about $6 to $8 a month on a $160 bill. The order is meant to keep this one data center's power costs off the bills of regular DTE residential customers, but critics argue the fast, largely ex parte approval process did not fully test that promise.
DTE Electric filed a new rate case in 2026 asking for a 474.3 million dollar increase, about 9.7 percent more from residential customers, for a period starting March 2027. DTE separately offered to pause future rate hike requests for two years if this case gets a constructive outcome and its Saline Township data center opens on time, an offer Attorney General Dana Nessel called a ransom note that ties ordinary ratepayer relief to data center approvals. On August 28, 2026 Nessel filed testimony recommending the commission cut the increase to about 134.5 million dollars, roughly 2 percent, and require data centers to be billed as a separate rate class that covers their own added grid costs; as of October 2026 the case remains pending, with Commission staff still revising the case schedule and a decision expected around February 2027.
Every Michigan rate case in dollars a month, with hearing dates: willmybillgoup.com, our rate case tracker.