Added as filed
Patmos Independence Technology Campus (EastGate Commerce Center)
Patmos. Filed, 100 MW
Patmos is under contract to convert an existing warehouse, EastGate Commerce Center Building A2 on South Little Blue Parkway in Independence, into a roughly 285,000 square foot data center that would start at 17.5 megawatts and could grow to 100 megawatts. Patmos applied for its building permit in June 2026, before the city later adopted a data center moratorium, so the project is proceeding under the city's prior rules, though the city does not yet have enough spare power capacity and would need to approve an infrastructure upgrade or let Patmos add onsite backup generation. The Independence City Council postponed a vote on assigning the property's leasehold interest to November 2, 2026, with the land deal expected to close November 12, 2026 pending that approval.
How far is it from you?
Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.
Follow this project
One free email when Patmos Independence Technology Campus (EastGate Commerce Center) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get the address report for $19.
- Status
- Filed
- Operator
- Patmos
- Applicant on record
- Patmos
- Location
- 2500 S Little Blue Parkway, Independence, MO, Jackson County, MO
- Size
- 100 MW, 285,000 sq ft
- Cooling
- Not reported
- Utility
- Independence Power & Light
- Next hearing
- November 2, 2026, Independence City Council (past)
- First reported
- 2026-06
- Last updated
- October 26, 2026
What happens next
Still to come: public hearings, a rezoning or permit vote, and a utility interconnection agreement.
Sources
- Patmos to build new data center in Independence, Missouri, as city moratorium discussed, Data Center Dynamics
- Independence City Council postpones decision on 2nd data center project in Little Blue Valley, KSHB
- Amid moratorium, Independence passes new rules for data center, battery storage zoning, KSHB
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 100 MW facility would draw roughly 317,000 to 1.1 million gallons of water a day, about what 3,600 households use.
For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.
History
Other tracked projects within 25 miles
Common questions
Where is the Patmos Independence Technology Campus (EastGate Commerce Center) data center?
It is in Independence, Jackson County, MO.
Has the Patmos Independence Technology Campus (EastGate Commerce Center) data center been approved?
Not yet. An application has been filed and has not been decided.
How big is the Patmos Independence Technology Campus (EastGate Commerce Center) data center?
Reported size: 100 MW, 285,000 square feet.
When is the next public hearing?
November 2, 2026, Independence City Council.
Corrections and tips: use the address in the footer. We link every claim to its source.