Is a Data Center Coming

Floyd County, GA

Project Firecracker

Microsoft. Approved, 422 MW

Microsoft is investing about 1 billion dollars in a data center campus on about 349 acres off Huffaker Road outside Rome, first announced October 30, 2023, with the Rome-Floyd Development Authority issuing bonds and a 12 year partial property tax abatement. The project, known internally as Project Firecracker and referenced as ATL80 in a Development of Regional Impact application Microsoft filed on October 20, 2026, is planned as three buildings totaling about 1,659,000 square feet with roughly 422 megawatts of capacity from Georgia Power, an estimated 360 million dollar buildout value, and about 35 million dollars a year in projected local tax revenue. Microsoft has targeted 2027 to 2028 for the campus to go live and expects to create at least 150 jobs.

How far is it from you?

Free. Every site we track within 25 miles of your address, nearest first, with how far each one is.

Status
Approved
Operator
Microsoft
Applicant on record
Microsoft
Location
Huffaker Road, Rome, Floyd County, GA
Size
422 MW, 349 acres, 1,659,000 sq ft
Cooling
Not reported
Utility
Georgia Power
First reported
2023-10-30
Last updated
October 26, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 422 MW facility would draw roughly 1.3 million to 4.8 million gallons of water a day, about what 15,400 households use.

Base rate freeze through 2028 (docket 44280) holds base rates flat from July 2025. Fuel and storm riders are separate and can still move. Real-time pricing revenue credit and cost allocation review (docket 57171) is pending before the commission without a published residential figure yet. 2026 fuel and storm cost settlement (docket 44280, 56765) takes about $4.04 a month off a typical bill from June 2026.

For how far this is from your own address, check it here. For what this site could mean for one street address, see the address report, $19.

History

November 3, 2026

Size: not reported to 422 MW

Other tracked projects within 25 miles

Common questions

Where is the Project Firecracker data center?

It is in Rome, Floyd County, GA.

Has the Project Firecracker data center been approved?

Yes, it has been approved.

How big is the Project Firecracker data center?

Reported size: 422 MW, 349 acres, 1,659,000 square feet.