T5 Data Centers Nampa (Park 84 conversion)

T5 Data Centers. Approved. 8 MW.

T5 Data Centers won a conditional use permit from the Nampa Planning and Zoning Commission in August 2025 to convert an existing single story, more than 80,000 square foot industrial building at 8300 Birch Lane, inside the Park 84 light industrial park, into a small single tenant data center. Company representatives described it as a modest networking facility next to the region's much larger campuses, starting around 5 megawatts with room to grow to about 8.25 megawatts over two to five years, staffed by roughly 11 employees with security levels that could reach five people on some shifts.

Status
Approved
Operator
T5 Data Centers
Applicant on record
T5 Data Centers
Location
8300 Birch Lane, Nampa, ID, Canyon County, ID
Size
8 MW, 80,000 sq ft
Cooling
Not reported
Utility
Idaho Power
First reported
2025-08
Last updated
September 24, 2026

What happens next

Still to come: permits and construction. Builders do not always announce a construction start date in advance.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 8 MW facility would draw roughly 26,000 to 94,000 gallons of water a day, about what 300 households use.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

History

September 25, 2026

Added as approved

Other tracked projects within 25 miles

Common questions

Where is the T5 Data Centers Nampa (Park 84 conversion)?

It is in Nampa, Canyon County, ID.

Has the T5 Data Centers Nampa (Park 84 conversion) been approved?

Yes, it has been approved.

How big is the T5 Data Centers Nampa (Park 84 conversion)?

Reported size: 8 MW, 80,000 square feet.

Is it near you?