Centra Reno Data Center (RNO2 / Keystone)
Centra. Under construction. 12 MW.
Centra's data center at 265 Keystone Avenue in Reno, known during permitting as the Keystone Data Center, is a 3.26-acre, two-story, roughly 91,200 square foot building that won a conditional use permit on January 15, 2025 over objections from more than 20 nearby residents about noise, power and water strain. Centra has since broken ground on the project as its second Reno-area facility, next to an existing data center built in 1999.
Follow this project
One free email when Centra Reno Data Center (RNO2 / Keystone) changes status, a hearing is scheduled, or a comment deadline opens.
Unsubscribe with one click. We do not sell the list.
Buying or living near this site? Get an address report.
- Status
- Under construction
- Operator
- Centra
- Applicant on record
- Centra
- Location
- 265 Keystone Ave, Reno, NV 89503, Washoe County, NV
- Size
- 12 MW, 3 acres, 91,200 sq ft
- Cooling
- Not reported
- Utility
- NV Energy
- First reported
- 2024-12
- Last updated
- August 19, 2026
What happens next
The site is under construction. The next step is opening.
Sources
- Keystone Data Center Gets New Permit Approval Despite Community Opposition, Our Town Reno, 2025-01-18
- Keystone Data Center Planned in Reno, NVBEX, 2024-12-18
- Centra breaks ground on second Reno data center, Data Center Dynamics, 2026
What it would mean nearby
The cooling design has not been reported. If it uses evaporative cooling, a 12 MW facility would draw roughly 38,000 to 137,000 gallons of water a day, about what 400 households use.
2026 fuel cost filings is pending; NV Energy says it would take about $4 to $6 off a typical monthly bill. Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028. Sierra Pacific 2024 general rate case (docket 24-02026) adds about $2.00 a month to a typical bill from October 2024.
For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.
Other tracked projects within 25 miles
Common questions
Where is the Centra Reno data center?
It is in Reno, Washoe County, NV.
Has the Centra Reno data center been approved?
Yes, it was approved and is now under construction.
How big is the Centra Reno data center?
Reported size: 12 MW, 3 acres, 91,200 square feet.
Is it near you?
Corrections and tips: use the address in the footer. We link every claim to its source.