Fleet Data Centers (filed as Tract). Under construction. 230 MW.

Fleet Data Centers, backed by a 4.6 billion dollar senior secured notes deal, broke ground on two adjacent campuses (South Valley and Peru Ridge/Peru Shelf) within Tract's Tahoe Reno Industrial Center land position in Storey County, targeting a combined 230 megawatts of critical compute power in an initial phase. Tract controls well over 1,000 additional acres nearby for further expansion. In September 2026 Fleet won conditional approval from the Public Utilities Commission of Nevada to build two private natural gas power plants as bridge power for the campuses, a 144 megawatt South Valley Energy Generation Facility and a 218 megawatt Peru Ridge Self-Generation Project, meant to run 2 to 3 years until NV Energy can serve the site directly; the approval still needs sign-off from the Nevada Division of Environmental Protection and Storey County.

Status
Under construction
Operator
Fleet Data Centers
Applicant on record
Tract
Location
Tahoe Reno Industrial Center, Storey County, NV, Sparks, Storey County, NV
Size
230 MW
Cooling
Not reported
Utility
NV Energy
First reported
2026-06
Last updated
September 28, 2026

What happens next

The site is under construction. The next step is opening.

Sources

What it would mean nearby

The cooling design has not been reported. If it uses evaporative cooling, a 230 MW facility would draw roughly 729,000 to 2.6 million gallons of water a day, about what 8,400 households use.

2026 fuel cost filings is pending; NV Energy says it would take about $4 to $6 off a typical monthly bill. Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028. Sierra Pacific 2024 general rate case (docket 24-02026) adds about $2.00 a month to a typical bill from October 2024.

For how far this is from your own address, check it here. For a noise, water, and power bill estimate for one address, see the address report.

Other tracked projects within 25 miles

Common questions

Where is the Fleet Data Centers South Valley and Peru Ridge Campuses?

It is in Sparks, Storey County, NV.

Has the Fleet Data Centers South Valley and Peru Ridge Campuses been approved?

Yes, it was approved and is now under construction.

How big is the Fleet Data Centers South Valley and Peru Ridge Campuses?

Reported size: 230 MW.

Is it near you?