Novva Tahoe Reno Data Center

Novva Data Centers. Operating. 60 MW.

Novva Data Centers launched its 300,000 square foot, 60 megawatt Tahoe Reno data center on a 20-acre campus in the Tahoe Reno Industrial Center in July 2025, its fourth completed facility nationally. The building includes six 10 megawatt data halls, water-free cooling, and a dedicated 100 megawatt substation from NV Energy.

Status
Operating
Operator
Novva Data Centers
Applicant on record
Novva Data Centers
Location
Tahoe Reno Industrial Center, Storey County, NV, Sparks, Storey County, NV
Size
60 MW, 20 acres, 300,000 sq ft
Cooling
Air cooled
Utility
NV Energy
First reported
2025-07
Last updated
August 19, 2026

Sources

What it would mean nearby

2026 fuel cost filings is pending; NV Energy says it would take about $4 to $6 off a typical monthly bill. Nothing here changes a bill today. What matters is whether the large load contract survives intact; if it is weakened, the cost of plants built for data centers starts showing up in the next general rate cases around 2027 and 2028. Sierra Pacific 2024 general rate case (docket 24-02026) adds about $2.00 a month to a typical bill from October 2024.

For a noise estimate and the three distance rings, check your own address.

Other tracked projects within 25 miles

Is it near you?

Corrections and tips: use the address in the footer. We link every claim to its source.