King George supervisors approved a rezoning in February 2026 for 13 data center buildings totaling 6.5 million square feet on about 300 acres at Kings Highway and Bloomsbury Road.
Data centers in King George County
We track 3 projects inside King George County and 7 more within 25 miles of it. For a distance-specific answer, check your own address.
In King George County
King George supervisors unanimously approved Dahlgren West, the county's first data center project, a 485-acre campus on the north side of Route 301 planned for ten two-story buildings up to 70 feet tall.
Amazon Data Services planned a large campus of up to 19 buildings and 7.5 million square feet on the former Birchwood Power Plant site. The project remains stalled by the circuit court dispute over the original performance agreement, with trial dates now set for September 28-29, 2026. Separately, Amazon has withdrawn its application to renew a state permit that would have let it pump up to 6.4 million gallons of groundwater a year from the Potomac aquifer for non-cooling uses, after Senator Richard Stuart urged the Department of Environmental Quality to deny it, citing a state report finding little remaining aquifer capacity; Amazon says it will pursue alternate water sources as advised by DEQ.
Within 25 miles of King George County
Power bills in King George County
Most of the county is served by Dominion Energy.
Deferred fuel cost recovery (docket PUR-2026-00078) is pending; Dominion Energy says it would add about $7 to $9 to a typical monthly bill. Data center cost allocation and transmission rider (docket PUR-2026-00056) adds about $0.94 a month to a typical bill, decided August 1, 2026. 2025 biennial review base rate increase (docket PUR-2025-00058) adds about $11.24 a month to a typical bill from January 2026.
This case covers Dominion's roughly 922 million dollar deferred fuel cost shortfall, with Dominion proposing to recover it from customers over seven to ten years. A State Corporation Commission hearing examiner has reportedly recommended the shorter seven year repayment option, but no final SCC order had been issued as of September 2, 2026, with commissioners expected to rule by the end of September 2026.
Every Virginia rate case in dollars a month, with hearing dates: willmybillgoup.com, our rate case tracker.
Alerts for King George County
An email when a filing, hearing, or status changes within 25 miles of the county seat. For a tighter radius, check your own address and subscribe there.
Unsubscribe with one click. We do not sell the list.
Want this worked out for one address? The address report covers noise, water, your power bill, and what is being planned nearby. See the address report.