ProjectOperatorCountyStateStatusMWNext dateUpdated
Aligned Data Centers Pataskala Proposal Aligned Data Centers Licking OH Filed Aug 19, 2026
Aligned Energy Data Center PHX06 Aligned Data Centers Maricopa AZ Filed Aug 19, 2026
Bitdeer Shalersville Data Center Proposal Bitdeer Technologies Group Portage OH Filed 750 Aug 19, 2026
Cologix Johnstown Campus Cologix Licking OH Filed 800 Aug 19, 2026
Cologix Orange Township Campus Cologix Delaware OH Filed Aug 19, 2026
Compass PHX II Campus Compass Datacenters Maricopa AZ Filed 108 Aug 19, 2026
Crusoe-Microsoft Abilene AI Factory Expansion Crusoe Energy Taylor TX Filed Aug 19, 2026
EdgeConneX Ashville Data Center EdgeConneX Pickaway OH Filed 800 Aug 19, 2026
EdgeConneX Cedar Creek Data Center II EdgeConneX Bastrop TX Filed Aug 19, 2026
Google Armstrong County Data Center Google Armstrong TX Filed Aug 19, 2026
Google Haskell County Data Centers Google Haskell TX Filed Aug 19, 2026
Google Midlothian Data Center Campus (Fifth Building) Google Ellis TX Filed Aug 19, 2026
Hut 8 Beacon Point Data Center Hut 8 Nueces TX Filed Aug 19, 2026
La Osa Project (Vermaland) Vermaland LLC Pinal AZ Filed 1000 Hearing Aug 26 Aug 19, 2026
Microsoft Granger Data Center Microsoft St. Joseph IN Filed Aug 19, 2026
Microsoft Perry Township Data Center Microsoft Stark OH Filed Aug 19, 2026
Microsoft PHX-83 (El Mirage campus expansion) Microsoft Maricopa AZ Filed Aug 19, 2026
Microsoft San Antonio Data Center Microsoft Bexar TX Filed Aug 19, 2026
Microsoft SAT 82 Data Center Microsoft Medina TX Filed Aug 19, 2026
Midland County Gas-Powered Data Center Platform Operator not disclosed Midland TX Filed 150 Aug 19, 2026
Mt. Comfort Technology Park EQT Real Estate Hancock IN Filed Aug 19, 2026
NTT Global Data Center Mesa (Pecos and Crismon) NTT Global Data Centers Maricopa AZ Filed Aug 19, 2026
Project Hutto Data Center Zydeco Williamson TX Filed 70 Aug 19, 2026
Project Infrared (CORVA) Data Center CORVA Infrastructure Services Lubbock TX Filed 27 Aug 19, 2026
Sunbury Area Data Center Campus (Trenton Township) City of Sunbury Delaware OH Filed Aug 19, 2026
Tract Caldwell Valley Technology Park Tract Caldwell TX Filed 4000 Aug 19, 2026
WhiteFiber Yadkin County campuses (NC-2, NC-3) WhiteFiber Yadkin NC Filed 60 Aug 19, 2026
300 Jones Road data center Operator not disclosed Spartanburg SC Filed Hearing Sep 21 Aug 17, 2026
Gardner Property Data Centers JK Land Holdings (Chuck Kuhn) Prince William VA Filed Aug 17, 2026
Project Oak Operator not disclosed Coweta GA Filed Hearing Aug 25 Aug 13, 2026
AWS Warren County Data Center Amazon Web Services Warren MS Filed Aug 1, 2026
Crossroads Tech Campus Operator not disclosed Spotsylvania VA Filed Aug 1, 2026
Beacon Data Centers Mobile County Campus Beacon Data Centers Mobile AL Filed Jul 30, 2026
Haven Oak Tech Park Tract Dinwiddie VA Filed Jul 30, 2026
Tuckahoe Technology Park Tract Goochland VA Filed 900 Jul 27, 2026
Brown Farm Road Data Center Oakley Real Estate Partners Bartow GA Filed Hearing Aug 24 Jul 22, 2026
Dulles Technology Park Operator not disclosed Loudoun VA Filed Jul 1, 2026
Project Indo Operator not disclosed Bartow GA Filed 2000 Jul 1, 2026
Spring Valley Tech Park Operator not disclosed Loudoun VA Filed Jul 1, 2026
Forest Lane Data Center Operator not disclosed Stafford VA Filed Jun 15, 2026
Google LaGrange Data Center Google Troup GA Filed Apr 21, 2026
Virginia Technology Park Equus Capital Partners Ltd. Frederick VA Filed Apr 10, 2026
Bridgeport Data Centers Operator not disclosed Coweta GA Filed Apr 1, 2026
Hickman Property Data Center Campus East Village Dothan, LLC Carroll GA Filed Mar 1, 2026
PCC-DeKalb Data Center Campus PCC-DeKalb, LLC DeKalb GA Filed Jan 1, 2026
Project Avemore Atlas Development LLC Carroll GA Filed Jan 1, 2026
Rockdale Technology Part 1 SDP Acquisitions Rockdale GA Filed Jan 1, 2026
River Park (Highway 16) Operator not disclosed Butts GA Filed Dec 1, 2025
Project West WHP-GA LLC Troup GA Filed 600 Nov 26, 2025
Newton County Technology Park (Social Circle Technology Park) TPA Group / SC Infrastructure LLC Newton GA Filed May 26, 2025
Gregory Road Data Center Campus JBW Investments LLC / JF Land Investments LLC Newton GA Filed Mar 28, 2025
Rocky Creek Road Data Center 0 Rocky Creek Road, LLC Henry GA Filed Mar 28, 2025
Strickland Road Farm Data Center Strickland Road Farms, LLC Henry GA Filed Mar 28, 2025
Embry Development Villa Rica site Embry Development Company Carroll GA Filed Feb 13, 2025
AWS Butts County - Building 1 Amazon (AWS) Butts GA Filed 69 Jan 7, 2025
Stonewall Tell Data Center (RSC) RSC Investment Management LLC Fulton GA Filed Dec 10, 2024
Project Pegasus (Coweta County, T5) T5@Atlanta IV, LP Coweta GA Filed Feb 1, 2024
EdgeCore Culpeper Campus EdgeCore Digital Infrastructure Culpeper VA Filed 432
EdgeCore Louisa County Campus EdgeCore Digital Infrastructure Louisa VA Filed 1100
Mattameade Tech Campus (formerly Orrock Tech Campus) Amazon Web Services Caroline VA Filed
Microsoft Boydton Expansion Microsoft Mecklenburg VA Filed
Winchester Gateway Operator not disclosed Frederick VA Filed